Back to filtered results
XRN 4542
XRN 4542
Changes to the Shipper Portfolio Summary Report (new fields and removal of fields no longer applicable)
Last Updated
|
01 Jan 2019 |
Status
|
Implemented
|
Release Type
|
Ad-hoc |
Implementation Date
|
16
Nov
2018
|
Proposer | Gazprom | Impacted DSC service area |
Service Area 1 (Previous Dec 18 – Mar 21) Manage Supply Point Registration |
Customer Change Team Leader | uklink@xoserve.com |
Summary
Current Shipper Portfolio Summary Report was introduced some time back and many of fields supplied are no longer relevant due to industry change i.e. removal of interruptible supply points (so blank). As Nexus is now implemented the PSR report needs to provide information relevant to Supply Point Class. Also to provide information around AMR equipment and Smart Meters recorded on the register
Impacted Customer Types
- Shipper
Documents
Document title | Last updated | Type |
---|---|---|
XRN4542 Change Proposal | 21/Mar/2019 | |
XRN4542 BER | 03/Jan/2019 | |
XRN4542 (CCR) | 03/Jan/2019 |
Timeline
Initial Review
Capture
Solution Consultation
Awaiting Delivery
In Delivery
Implemented
Contact the Change Team
Need to get in touch with a member of the Change Team?
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.