Image of back arrow Back to filtered results

XRN 6081
Meter Read Service Improvements

Last Updated
30 Apr 2026
Status
Current
Release Type
Ad-hoc
Implementation Date
TBC
Proposer Xoserve Impacted DSC service area

Service Area 4 (Current Apr 21)

Meter Read/Asset processing

Customer Change Team Leader uklink@xoserve.com

Summary

This Change Proposal will act as a parent to group the individual Change Proposals and as a central point of reference for customers.

The coverage of this change proposal is around meter reads and how reconciliation values are calculated following their receipt. As such, it is foreseen that the impacted parties would be
Shippers and DNs.

Subsequent Change Proposals will be raised to address issues identified in the meter read and reconciliation processes. These are:

A

Fix Historic NDM Check to Check Reconciliation Periods - Tactical Solution

B

Reconciliation of Multiple Read Replacements – Historic Reporting and Tactical Solution

C

NDM Check to Check Reconciliation – Enduring Solution

D

Reconciliation of Multiple Read Replacements – Enduring Solution

E

Read Inserted Prior Expected Class 4 Opening Read - Volume and Energy Calculation

F

Read Validation where no Actual Read Present in Previous Class Period

G

Reconciliation of Class Change with subsequent Shipper Transfer and Class Change

H

RGMA Read Validation where Site Flagged as AMR

I

NDM Opening Read Estimation Based on Read with a Positive Through The Zero Count

J

Twin Stream Volume Aggregation

XRN 6081.A
Fix Historic NDM Check to Check Reconciliation Periods - Tactical Solution

Current

View Change Proposal
The objectives of this Change Proposal are to: 1. Review and analyse all C2C periods, currently available for adjustment, to establish the impact of the defined problem2. Correct the position of the incorrect reconciliations, identified in step 1, th...
XRN 6081.B
Reconciliation of Multiple Read Replacements – Historic Reporting and Tactical Solution

Current

View Change Proposal
The coverage of this change proposal is around the reconciliation process and invoicing of this to Shipper Users. Where multiple Shipper readings, for the same MPRN, are submitted on the same date, they may not be correctly utilised within the reconc...

Impacted Customer Types

  • Shipper
  • DNO

Documents

Document title Comment Last updated CHMC outcome
Change Proposal Awaiting ChMC approval   30/04/26 N/A
Initial Review Stage not yet reached   N/A
High Level Solution Options Stage not yet reached   N/A
Solution Review Stage not yet reached   N/A
Detailed Design Stage not yet reached   N/A
Evaluation Quotation Reports (EQR) Stage not yet reached   N/A
Business Evaluation Reports (BER) Stage not yet reached   N/A
Change Completion Reports (CCR) Stage not yet reached   N/A

Timeline

Change Proposal raised
30/04/26
Status Awaiting ChMC approval 
Change development
Solution development
Detailed design
Awaiting delivery
In delivery
Change implemented

Contact the Change Team

Need to get in touch with a member of the Change Team?

You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.