XRN 5615
Establishing/Amending a Gas Vacant Site Process (Modification 0819)

Last Updated
28 Oct 2024
Status
Current
Release Type
Major
Implementation Date
08 Nov 2024
Proposer Centrica Impacted DSC service area

Service Area 2 (Current Apr 21)

Monthly AQ Processes

Customer Change Team Leader uklink@xoserve.com

Summary

This Change Proposal has been raised to deliver the requirements outlined in Modification 0819 Establishing/Amending a Gas Vacant Site Process.

Modification 0819 aims to create a new process for Vacant Product Class 4 Non-Daily Metered (NDM) sites which would allow Shippers to receive commodity and performance relief (immediately) and capacity relief (after 12 months at vacant status) for sites in their ownership.

A SMP must meet the Vacant Site criteria outlined in Modification 0819 and associated guidance documentation for the Shipper to have the ability to effectively manage their Settlement Performance Obligations and Transportation Costs.

 

Please note that this change and funding aligns to 3 service areas, service area 2, 3 and 10. 

Impacted Customer Types

  • Shipper
  • DNO
  • IGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal CP raised 10/03/2023 Approved at ChMC 08/03/2023
Initial Review Stage not required   N/A
DSG Discussion

Minutes 22nd July 2024

Minutes 21/10//24

19/02/2024

28/10/2024

 

Design Considerations

High Level Solution Options N/A 12/02/2024 N/A
Solution Review Change Pack 3256 - LO - PO 12/02/2024 ChMC approved 13/03/24
Detailed Design Change Pack 3295 - LO - PO 09/08/2024 Approved at ChMC 07/08/24
Evaluation Quotation Reports (EQR) Stage not required   N/A
Business Evaluation Reports (BER) Approved  02/09/2024 Approved at ChMC 07/08/24
November 24 Release e-learning Online e-learning course 15/10/2024 N/A
Change Completion Reports (CCR) Stage not yet reached   N/A

Timeline

Initial Review
CP Raised 23/02/23
Status For approval at ChMC 08/03/2023 to go into development
Capture
Approved into development 08/03/23
Status ChMC approved CP on 08/03/2023
Solution Consultation
Solution Option Change Pack issued 12/02/24
Status ChMC approved 13/3/24
Awaiting Delivery
Detailed Design Change Pack Issued 15/07/24
Status ChMC approved 07/08/24
In Delivery
ChMC approved into Delivery 07/08/24
Status ChMC approved into Scope for November 24
Implemented
Expected: 00/00/00
Status Awaiting