Last Updated
|
18 May 2021 |
Status
|
Implemented
|
Release Type
|
Minor |
Implementation Date
|
20
Mar
2021
|
Proposer | CDSP | Impacted DSC service area |
N/A Not applicable |
Customer Change Team Leader | uklink@xoserve.com |
Summary
This XRN5294 is the Parent XRN for Minor Release Drop 9.
There are 2 changes within this drop:
XRN 5080
Failure to Supply Gas (FSG/GSOP1) – System Changes
Implemented |
This change requires various amendments to the current FSG/GSOP1 service provided by Xoserve.
- Scheduled payment frequency from fortnightly to weekly.
This would accommodate the reduction from 20 to 10 working days for settlement after an FSG eve...
|
XRN 5135
DNO and NTS Invoices to Shippers and DNs VAT compliance
Implemented |
Invoices issued to DNs and the invoices issued to Shippers on behalf of DNs are missing some of the details set out in https://www.gov.uk/vat-record-keeping/vat-invoices
Specifically, customer name and address and vendor address. As such the invoice...
|
Impacted Customer Types
- IGT
- NGT
- Shipper
- DNO
Documents
Document title | Last updated | Type |
---|---|---|
CCR for 5294 | 18/May/2021 | |
XRN5294 - Change Proposal | 22/Dec/2020 |
Timeline
Initial Review
Start:
13/01/21
Status
To be presented at Jan ChMC for information
Capture
Expected:
31/12/20
Status
Changes progressing through Capture
Solution Consultation
Expected:
00/00/00
Status
Awaiting
Awaiting Delivery
Expected:
00/00/00
Status
Awaiting
In Delivery
Expected:
00/00/00
Status
Awaiting
Implemented
Implemented on
20/03/21
Status
Implementation complete