XRN 5143
Discharge of Cadent, WWU and NGN NDM sampling obligations by the CDSP

This XRN is part of XRN 5575 March 23 Adhoc Release
Last Updated
14 Jul 2023
Status
Implemented
Release Type
Ad-hoc
Implementation Date
01 Apr 2023
Proposer Cadent Gas Impacted DSC service area

TBC

To be confirmed

Customer Change Team Leader uklink@xoserve.com

Summary

Xoserve are closer to the NDM demand estimation process than the DNs and have a close relationship with Shippers in this regard, they are therefore better placed to ensure the correct coverage across each EUC Band and Class.

Discharge of Cadent, WWU and NGN NDM Sampling UNC obligations (as per UNC TPD H1.6) for EUC Bands 3-9 by the CDSP. Note the CDSP already carries out NDM sampling for EUC Bands 1 and 2 so this change is simply an extension to the current CDSP process.

Impacted Customer Types

  • Shipper
  • DNO

Documents

Document title Comment Last updated CHMC outcome
Change Proposal N/A 27/03/2020 Approved at ChMC on 08/04/2020
Initial Review Stage not required N/A N/A
High Level Solution Options HLSO/Solution published directly to Cadent, WWU and Northern Gas Networks 31/08/2022 N/A
Solution Review HLSO/Solution published directly to Cadent, WWU and Northern Gas Networks 31/08/2022 N/A
Detailed Design Detailed Design Change Pack published directly to Cadent, WWU and Northern Gas Networks 19/12/2022 N/A
Evaluation Quotation Reports (EQR) Stage not required N/A N/A
Business Evaluation Reports (BER) N/A 28/03/2023 Approved at ChMC 09/11/2022
XRN 5575 e-learning Online e-learning session 01/03/2023 N/A
Change Completion Reports (CCR) N/A 14/07/2023 Approved at ChMC 12/07/23

Timeline

Initial Review
Start: 00/00/00
Status Awaiting
Capture
Expected: 08/04/20
Status Approved into Capture
Solution Consultation
Expected: 31/08/22
Status HLSO published directly to Cadent, WWU and Northern Gas Networks
Awaiting Delivery
Expected: 19/12/22
Status Detailed Design Change Pack published directly to Cadent, WWU and Northern Gas Networks
In Delivery
Expected: 25/03/23
Status First set of planned activities successfully completed on 25/03/2023
Implemented
Implementation successful 01/04/23
Status Implementated