Image of back arrow Back to filtered results

XRN 5316
Rejecting a replacement read with a pre-Line in the Sand (LIS) read date

This XRN is part of XRN 5647 Minor Release Drop 11
Last Updated
22 Sep 2023
Status
Implemented
Release Type
Ad-hoc
Implementation Date
22 Sep 2023
Proposer Xoserve Impacted DSC service area

N/A

Not applicable

Customer Change Team Leader uklink@xoserve.com

Summary

This change seeks to reject replacement Meter Reads, using an existing rejection code, provided by either the DMSP or Shipper User where the read date is prior to the current LIS date. 

The LIS date is set each year and estimated reads are generated for 01/04/YYYY where no reading(s) exist for 3 years prior to the new LIS date and no reading exists after this date. Therefore, where there is no estimated or actual LIS read, then the read immediately prior to the LIS date will remain a valid read to be replaced and subject to all other read validations and reconciliation/invoicing processes. In these cases, re-reconciliation will be triggered to correct the post LIS period, only.

Impacted Customer Types

  • DMSP
  • Shipper

Documents

Document title Comment Last updated CHMC outcome
Change Proposal N/A 16/06/2022 Approved at ChMC on 08/06/2022
Initial Review Stage not required N/A N/A
DSG Discussion N/A 27/06/2022 N/A
High Level Solution Options Stage not required N/A N/A
Solution Review Stage not required N/A N/A

Detailed Design

Detailed Design - Re-issue

Comm ref: 3050.3 -RT -PO

Comm ref: 3069.1 - KL - PO

18/07/2022

15/08/2022

Deferred at ChMC on 13/07/2022

Approved at ChMC on 10/08/2022

Evaluation Quotation Reports (EQR) Stage not required N/A N/A
Business Evaluation Reports (BER) Stage not required N/A N/A
Change Completion Reports (CCR) Stage not yet reached N/A N/A

Timeline

Initial Review
Change Proposal Raised 31/05/22
Status Approved at ChMC on 08/06.2022
Capture
Approved at ChMC 08/06/22
Status ChMC approved into Capture
Solution Consultation
Expected: 00/00/00
Status Stage not required
Awaiting Delivery
Change Pack re-issued, design in consultation 10/08/22
Status Detailed Design Change Pack was approved at ChMC on 09/08/2022
In Delivery
Expected: 09/08/23
Status In Delivery as part of Minor Release 11
Implemented
Expected: 22/09/23
Status Successfully Implemented

Contact the Change Team

Need to get in touch with a member of the Change Team?

You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.