Image of back arrow Back to filtered results

XRN 5941
Performance Assurance Committee (PAC) – Audit Performance Assurance Technique (PAT) Request

Last Updated
30 May 2025
Status
Current
Release Type
Ad-hoc
Implementation Date
TBC
Proposer Xoserve Impacted DSC service area

Customer Change Team Leader uklink@xoserve.com

Summary

The Performance Assurance Committee have identified a need to enact Audit Performance Assurance Techniques (PAT), to enable an assessment to be carried out. The objective of this assessment is to evidence the level of compliance of CDSP deliverables associated to the Performance Assurance Committee.  

 

This Change Proposal will reserve funds from 2025/26 General Change budget, which will be utilised to enable 3rd party auditor activities to be conducted for the requested Audit Performance Assurance Technique. 

Impacted Customer Types

  • Shipper
  • DNO
  • IGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal CP Raised 30/05/2025

Presented at ChMC for approval on 11/06/2025

Initial Review Stage not yet reached   N/A
High Level Solution Options Stage not yet reached   N/A
Solution Review Stage not yet reached   N/A
Detailed Design Stage not yet reached   N/A
Evaluation Quotation Reports (EQR) Stage not yet reached   N/A
Business Evaluation Reports (BER) Stage not yet reached   N/A
Change Completion Reports (CCR) Stage not yet reached   N/A

Timeline

Change Proposal raised
30/05/25
Status CP to be presented at ChMC for approval on 11/06/2025
Change development
Solution development
Detailed design
Awaiting delivery
In delivery
Change implemented

Contact the Change Team

Need to get in touch with a member of the Change Team?

You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.