Summary

This change proposal has been raised to create a parent XRN for the Minor Release Drop 12 

There is 1 change within this release: XRN5582a Energy Invoice upload from UK Link to Gemini

  • The Neutrality Team within Xoserve need to ensure that UK Link Energy related invoices are recorded in Gemini to support cash collection, cash allocation and indebtedness monitoring processes. This is currently a manual process and can take the team up to 2 hours a day to complete. This change will automate the process and upload the invoices produced by Uk Link and upload them to Gemini.

Impacted Customer Types

  • Other

Documents

Document title Comment Last updated CHMC outcome
Change Proposal XRN5727 CP Raised 22/03/2024 Presented for information 13/03/24
Change Proposal XRN5582 CP Raised 22/03/2024 Approved at ChMC 13.03.24
Project Update   17/07/2024 N/A
DSG Discussion

Meeting - 25/03/24

Meeting - 22/04/24

29/04/2024 N/A
Business Evaluation Reports (BER) Stage not required   N/A
Change Completion Reports (CCR) Presented for approval at ChMC 11/07/24   Approved

Timeline

Change Proposal raised
21/02/24
Status To be presented to ChMC for information on 13/03/2024
Change development
21/02/24
Status stage not required
Solution development
21/02/24
Status stage not required
Detailed design
21/02/24
Status stage not required
Awaiting delivery
21/02/24
Status stage not required
In delivery
13/02/24
Status Approved at ChMC
Change implemented
10/05/24
Status Successfully implemented