Image of back arrow Back to filtered results

XRN 5379
Class 1 Read Service Procurement Exercise - MOD 0710

This XRN is part of XRN 5575 March 23 Adhoc Release
Last Updated
14 Jun 2023
Status
Implemented
Release Type
Ad-hoc
Implementation Date
25 Mar 2023
Proposer Xoserve Impacted DSC service area

TBC

To be confirmed

Customer Change Team Leader uklink@xoserve.com

Summary

Modification 0710S (related IGT Modification IGT148) was raised to obligate the CDSP to take on Class 1 Read Service provision on behalf of Shippers. This was to transfer the obligation to provide the Class 1 Supply Meter Point Read Service from the Transporters to the CDSP. The Change Proposal XRN5218 - CDSP provision of Class 1 read service was previously raised to carry out a novation of the existing contracts currently in place between the DNOs and the DMSPs, across to the CDSP. The decision was taken in June 2021, by the DNOs with the existing contracts in place for the Class 1 read service to continue with the current contracts and service as is until the contract expiry. The current contracts for this service expire on 31 March 2023.

To confirm, the CDSP will not novate the existing contracts for the Class 1 read service, the CDSP will run the procurement exercise to appoint a Service Provider and new contract as of 01 April 2023.

 

As a result of Modification 0710, it will be the responsibility of the CDSP to appoint a new Service Provider on behalf of Shippers, to provide the Class 1 Daily Read Service from 01 April 2023 onwards.

This Change Proposal has been raised in order to proceed with the procurement exercise to procure a new Service Provider for this service.

Impacted Customer Types

  • GT
  • IGT
  • Shipper
  • DNO

Documents

Document title Comment Last updated CHMC outcome
Change Proposal Approved 15/08/2022 Approved at ChMC on 07/07/2021
Initial Review Stage not required N/A N/A
DSG Discussion N/A 01/03/2023 N/A
High Level Solution Requirements Approved 08/09/2021 ChMC informed CoMC will oversee this.

Evaluation Quotation Reports (EQR)

Evaluation Quotation Reports (EQR) 2 

Approved 09/02/2022 Approved at ChMC 09/02/2022

Solution Review

Approved 15/08/2022 ChMC approved Solution Option 1 on 10/08/2022

High Level Solution Options

Approved 24/08/2022 ChMC approved Solution Option 1 on 10/08/2022

Detailed Design

Detailed Design

3098.7 - RT - PO

3139.4 - VO - PO

15/11/2022

13/03/2023

Approved at ChMC 09/11/2022

Presented for information to ChMC 08/03/2023

Business Evaluation Reports (BER) N/A 28/03/2023 Approved at ChMC 09/11/2022
XRN 5575 e-learning Online e-learning session 28/03/2023 N/A
Sample BRR file N/A 28/03/2023 N/A
Sample DMV file N/A 28/03/2023 N/A
Change Completion Reports (CCR) N/A 14/07/2023 Approved at ChMC 12/07/23

Timeline

Initial Review
Change Proposal Raised 24/06/21
Status Awaiting ChMC approval
Capture
ChMC approved into Capture 07/07/21
Status High Level Requirement Change Pack sent out August 21
Solution Consultation
Change Pack Issued 13/07/22
Status ChMC approved Solution Option 1
Awaiting Delivery
ChMC approved solution 13/07/22
Status Awaiting release assignment
In Delivery
Re-issue of Detailed Design Change Pack for information 13/02/23
Status First set of planned activities successfully completed on 25/03/2023
Implemented
Implementation successful 01/04/23
Status Implemented