XRN 5298
H100 Fife Project - Phase 1 (Initial Assessment)

Last Updated
28 Mar 2023
Status
Implemented
Release Type
Major
Implementation Date
25 Feb 2023
Proposer SGN Impacted DSC service area

Service Area 1 (Current Apr 21)

Manage Shipper Transfers

Customer Change Team Leader uklink@xoserve.com

Summary

SGN’s strategic ambition towards Net Zero includes a network innovation, ‘proof of concept’, project; H100 Fife. This project will see SGN injecting 100% hydrogen into a new, purpose-built network which will be located in parallel to the existing natural gas network. The H100 Fife Project is considered of national and strategic importance to demonstrating a capability to meet the UK Net Zero target ambition. 

 

SGN’s current plan anticipates H100 customers will commence offtaking hydrogen in Q2 2023.      

 

Xoserve is to collaborate with SGN to assess the UK-Link systems and process impacts and, develop high-level solution options.

Impacted Customer Types

  • Shipper
  • DNO
  • IGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal N/A 18/01/2021 Approved at ChMC on 10/02/2021
Initial Review Stage not used N/A N/A
High Level Solution Options

2918.4 - MT - PO

18/10/2021 Option 2 approved
Solution Review Approved 10/11/2021 Solution approved at ChMC on 10/11/2021
Detailed Design

3015.3 – RT - PO

06/01/2023

As the UNC MOD is still in consultation, ChMC voted to defer the approval on 11/05/2022

At ChMC 14/12/2022, the Detailed Design Change Pack was approved, following Ofgem approval of Modification 0799

Detailed Design

3078.1 - MT - PO

12/09/2022

Revised Detailed Design Change Pack issued and Presented at ChMC for information on 07/09/22

Evaluation Quotation Reports (EQR) Approved 25/11/2021 EQR approved 08/12/2021
Business Evaluation Reports (BER) N/A 28/03/2023 Approved at ChMC on 29/07/22
XRN 5298 e-learning Online e-learning session 09/02/2023 N/A
Change Completion Reports (CCR) Stage not yet reached N/A N/A

Timeline

Initial Review
Start: 18/01/21
Status Change Proposal raised
Capture
Approved to Capture 10/02/21
Status ChMC approved into Capture
Solution Consultation
Solution Change Pack Issued 18/10/21
Status ChMC approved solution 10/11/2021
Awaiting Delivery
Stage not used 00/00/00
Status Change moved directly to In Delivery
In Delivery
Adhoc Release Start Up 10/11/21
Status Project Initiation
Implemented
Expected: 25/02/23
Status Successfully Implemented