Last Updated
|
14 Jan 2019 |
Status
|
Implemented
|
Release Type
|
Minor |
Implementation Date
|
22
Feb
2019
|
Proposer | E.ON | Impacted DSC service area |
Service Area 15 (Previous Dec 18 – Mar 21) Demand Estimation |
Customer Change Team Leader | uklink@xoserve.com |
Summary
Following the approval of Modification 0654S / IGT110V - Mandating the provision of NDM sample data; this XRN has been created to deliver the system and reporting requirements.
In summary the modification requirements are (refer to mod for full details):
- Data cuts are to be provided to the CDSP in line with one of the following submission frequencies:
Monthly – By the 5th BD of each month (CDSPs preferred option to support continuous review of algorithm performance
Quarterly – By the 5th BD of January, April, July and October each year
Twice Yearly – By the 5th BD of April and October each year
Impacted Customer Types
- Shipper
Documents
Document title | Last updated | Type |
---|---|---|
XRN4770 CCR - NDM Sample Data | 15/May/2019 | |
XRN4770 | 15/Jan/2019 |