XRN 6070
DDP Release 1 2027/2028

Last Updated
26 Mar 2026
Status
Current
Release Type
Ad-hoc
Implementation Date
TBC
Proposer Xoserve Impacted DSC service area

Customer Change Team Leader uklink@xoserve.com

Summary

The request for this Change Proposal is to ensure that there is visibility to ChMC of the changes within scope of DDP Release 1 2026/27 – this aims to provide transparency so the rationale of the priority being applied to DDP scope can be clearly understood.

Release 1 will build on the analysis and design work in Release 6, and will begin development for multiple reports within the PARR which will be modified as described under these changes:

• XRN5923 – Updates to the PARR
• XRN5992 – HPM Report Changes
• UNC MOD0884

Impacted Customer Types

  • Shipper
  • DNO
  • IGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal Change Proposal Raised  26/03/26 N/A
Initial Review Stage not yet reached   N/A
High Level Solution Options Stage not yet reached   N/A
Solution Review Stage not yet reached   N/A
Detailed Design Stage not yet reached   N/A
Evaluation Quotation Reports (EQR) Stage not yet reached   N/A
Business Evaluation Reports (BER) Stage not yet reached   N/A
Change Completion Reports (CCR) Stage not yet reached   N/A

Timeline

Change Proposal raised
26/03/26
Status Awaiting ChMC approval 
Change development
Solution development
Detailed design
Awaiting delivery
In delivery
Change implemented

Contact the Change Team

Need to get in touch with a member of the Change Team?

You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.